Calendar Days Vs Working Days

Calendar Days Vs Working Days - 365 day activity is coming up as 150+ days and 12 mo is coming up as 340+ days. Hi planners is it possible to have variance target1 early finish in calendar days instead of working days ? If you use calendar days and not working days, you would need to alter your lags/durations to project an accurate date, each time the project slipped. For example, customer says we must hold a kickoff within 2 weeks of contract award. You could make a 7 days/week calendar and make that calendar the project calendar, which means that every task will get it by default. That means all days are going to be working days. By the way, i tried switching to a 7 day week calendar, but that didn't work.

I need it to plan using 14 calendar days. Hi planners is it possible to have variance target1 early finish in calendar days instead of working days ? Hi, i'm using project 2010 and i have a project that is created and planned using working days. If you use calendar days and not working days, you would need to alter your lags/durations to project an accurate date, each time the project slipped.

I need it to plan using 14 calendar days. I just want to show the number of days delayed. If you put in a month with a calendar that has 5 day work weeks and holidays. However, i do have a few task, such as like let material set for 8 days, that are dependent on calendar days. That means all days are going to be working days. By the way, i tried switching to a 7 day week calendar, but that didn't work.

If i entered 8d in the duration, it will count as 10 calendar days instead (or sometimes even 12 days, depending on whether the task starts on a friday, and. The contract i'm working on requires a project schedule showing the duration in calendar days. Currently i've tried to schedule a task that ends on a saturday and if auto shortens it to friday. I need it to plan using 14 calendar days. I just want to show the number of days delayed.

Hi, i'm using project 2010 and i have a project that is created and planned using working days. Thanks in advance for your input. If you use calendar days and not working days, you would need to alter your lags/durations to project an accurate date, each time the project slipped. I just want to show the number of days delayed.

Hi, I'm Using Project 2010 And I Have A Project That Is Created And Planned Using Working Days.

Thanks in advance for your input. Hi planners is it possible to have variance target1 early finish in calendar days instead of working days ? That means all days are going to be working days. The samples in the below picture show the same 25 calendar days interval yet they produce different working days (18 to 20 days) considering how many of the weekend days will fall into the given 25 days period.

365 Day Activity Is Coming Up As 150+ Days And 12 Mo Is Coming Up As 340+ Days.

By the way, i tried switching to a 7 day week calendar, but that didn't work. If you use calendar days and not working days, you would need to alter your lags/durations to project an accurate date, each time the project slipped. Currently i've tried to schedule a task that ends on a saturday and if auto shortens it to friday. In the past i used a formula that someone on one of these forums shared with me, but then i changed employers and lost that formula.

If You Put In A Month With A Calendar That Has 5 Day Work Weeks And Holidays.

They mean 14 calendar days (according to the instructions), but if i put fs+14d, or fs+2w, then project is interpreting that to mean 14 working days. However, i do have a few task, such as like let material set for 8 days, that are dependent on calendar days. The contract i'm working on requires a project schedule showing the duration in calendar days. Is there a way to change the format of the calendar from work days to calendar days?

Duration Are Entered In As Working Time And Sometimes You Want To See The Actual Days.

I just want to show the number of days delayed. For example, customer says we must hold a kickoff within 2 weeks of contract award. I need it to plan using 14 calendar days. If i entered 8d in the duration, it will count as 10 calendar days instead (or sometimes even 12 days, depending on whether the task starts on a friday, and.

In the past i used a formula that someone on one of these forums shared with me, but then i changed employers and lost that formula. Currently i've tried to schedule a task that ends on a saturday and if auto shortens it to friday. I just want to show the number of days delayed. Hi, i'm using project 2010 and i have a project that is created and planned using working days. For example, customer says we must hold a kickoff within 2 weeks of contract award.